Supporting the Sixth Division of the Communist Youth League in Shanxi Province
1. Tender conditions
The construction and supervision of the safe drinking water project for the company's joint infrastructure project for supporting the Communist Youth League's farm infrastructure in the sixth division of Shanxi Province has been approved by Shifa Development [2017] No. 69. The bidder is the sixth division of the Communist Youth League farm and the construction fund is from the counterpart support fund of Shanxi Province. With the group's self-raising, the project already has the conditions for tendering, and the construction and supervision of the project are now open for public bidding.
2. Project Overview and Bidding Scope
Construction site: 6th Division Communist Youth League Farm
Scale of construction: Two new pump houses, a construction area of ​​103 square meters, a water supply pipe network of 4,077 meters, and ancillary works such as 73 valves.
Plan duration: 72 calendar days (see the tender documents for details).
The scope of the tender: all the contents of the construction drawings.
Benchmarking: This bid is for two bids
A tender section: construction works.
Second bid section: Supervision project.
3. Bidder qualification requirements
3.1 A bid section: The bidder is required to have the qualification of third-grade or higher of the general contracting for construction of municipal public works, and has contracted the bidder who has similar or similar projects with the construction scale of the bidding project, engineering cost, etc. The bidder proposes the project manager Must have registered qualification as a registered public constructor of Grade 2 or above of municipal public utilities, have an effective safety production assessment certificate (Type B), and have not served as a project manager for other construction projects.
Second bid section: The bidder is required to have the professional contracting qualification for municipal public project supervision level B and above. The bidder intends to send the supervisory engineer of the municipal public utility project to have the registered practice qualification of the professional supervision engineer of the municipal public project, and has not served other supervisory projects.
3.2 The Commonwealth does not accept bids from the Consortium.
3.3 All bidders can apply for bids for the two bidding sections of the bidding project.
4. Bid registration
All construction and supervision companies with independent legal person qualifications and the above qualification requirements can apply for bids. The application deadline for the bids is March 15, 2017 to March 21, 2017 (excluding holidays), and 10:30 am daily. From 16:00 to 19:00 (Beijing time).
1. Tender conditions
The construction and supervision of the safe drinking water project for the company's joint infrastructure project for supporting the Communist Youth League's farm infrastructure in the sixth division of Shanxi Province has been approved by Shifa Development [2017] No. 69. The bidder is the sixth division of the Communist Youth League farm and the construction fund is from the counterpart support fund of Shanxi Province. With the group's self-raising, the project already has the conditions for tendering, and the construction and supervision of the project are now open for public bidding.
2. Project Overview and Bidding Scope
Construction site: 6th Division Communist Youth League Farm
Scale of construction: Two new pump houses, a construction area of ​​103 square meters, a water supply pipe network of 4,077 meters, and ancillary works such as 73 valves.
Plan duration: 72 calendar days (see the tender documents for details).
The scope of the tender: all the contents of the construction drawings.
Benchmarking: This bid is for two bids
A tender section: construction works.
Second bid section: Supervision project.
3. Bidder qualification requirements
3.1 A bid section: The bidder is required to have the qualification of third-grade or higher of the general contracting for construction of municipal public works, and has contracted the bidder who has similar or similar projects with the construction scale of the bidding project, engineering cost, etc. The bidder proposes the project manager Must have registered qualification as a registered public constructor of Grade 2 or above of municipal public utilities, have an effective safety production assessment certificate (Type B), and have not served as a project manager for other construction projects.
Second bid section: The bidder is required to have the professional contracting qualification for municipal public project supervision level B and above. The bidder intends to send the supervisory engineer of the municipal public utility project to have the registered practice qualification of the professional supervision engineer of the municipal public project, and has not served other supervisory projects.
3.2 The Commonwealth does not accept bids from the Consortium.
3.3 All bidders can apply for bids for the two bidding sections of the bidding project.
4. Bid registration
All construction and supervision companies with independent legal person qualifications and the above qualification requirements can apply for bids. The application deadline for the bids is March 15, 2017 to March 21, 2017 (excluding holidays), and 10:30 am daily. From 16:00 to 19:00 (Beijing time).
Lithium Ion Battery,5G Integrated Battery,Custom Ups Lithium Ion Battery,Communication Ladder Backup Battery